April 8 , 2008
During the month of March, major site work excavation included the cutting in of new roads and rough grading of new turf areas around the Conservatory. New asphalt on walking paths will be placed within the next three weeks, along with grading of new soil and installation of permanent fences.
In the Bride's Garden, walls, concrete pads, and the foundation on the fountains were placed during March. In April, walls and concrete work will continue. By month's end, some top soil will be brought in and some new trees will be set.
More progress was made on the interior of the new additions including the installation, priming and painting of drywall in the north addition. The Rulon wood ceiling was installed in the large event space. Wood trim are windows and doors, base and crown moldings are being installed as well.. Work on the new elevator and stairs continued. Installation of ceramic tile, stone flooring, and carpet is underway in April.
New openings from the Show House to the rooftop gardens will be cut in April and the doors installed.
PRIVACY POLICY | The emails collected from this page will be used for the expressed purpose of keeping the recipient current with the Growth. By Design. campaign and where we are with construction on the premises. We will not use your email for any other purpose, nor will we provide your email to any individual or company not associated with Franklin Park Conservatory and the Growth. By Design. campaign.
By providing your email address, you are giving Franklin Park Conservatory permission to send emails to the provided email address regarding Growth. By Design.
If you are interested in learning about upcoming events at Franklin Park Conservatory and would like to receive our e-newsletter, please visit the Franklin Park Conservatory's home page here.